Alongside the Oranjepolderweg, Warmte Netwerk Westland knowing over 3 thousand meters of warmth pipes within the coming duration.
The paintings is being performed through the contractor mixture of
A. Hak and Smit & Visser Hanab and can remaining till the second one quarter of 2023. Within the space, nearly ten greenhouse marketers will likely be hooked up to Warmtenetwerk Westland.

pijp

Get started connecting warmth pipes
On the finish of October, welding and connection of the already drilled warmth pipes began on Oranjepolderweg. On the identical time, the consortium of contractors additionally began preparatory paintings at the ‘space connections,’ the pipelines working from the primary pipeline to the longer term warmth exchanger to the related greenhouse. To permit each the relationship of warmth pipelines and the conclusion of the home connections, it’s every so often important to open up the street and inconvenience site visitors. Sadly, because of the fast distances and limited-diameter piping, no different way is possible.

Horizontal drilling
Lately, 3 of the six horizontal directional borings were effectively finished, and the rest borings will practice this calendar 12 months. Just lately, the primary a part of drilling quantity 4 close to the Inexperienced 2 Develop and CombiVliet nurseries was once performed. This will likely be adopted through a 2d segment on the identical location. All the way through those so-called ‘withdrawal moments,’ the Oranjepolderweg is totally closed to all site visitors.

Because of the aforementioned paintings at Oranjepolderweg, via site visitors is anticipated to be restricted till early March 2023, however all adjoining companies and houses will likely be obtainable. A diversion by way of Pettendijk or Korte Kruisweg has been selected – for causes of accessibility.

Supply: Warmte Netwerk Westland